GEBE is well on its way to solving its power generation problems and bringing an end to the load shedding that has been happening on the Dutch side.

Engine #19 was brought back online today adding 10.5 Megawatts back to the grid. Engines 18 & 20 had repairs made in October. The containerized 10MW units were fully operational in August and hopefully the new 20MW container units will be live by the end of November.

After all of this, maybe no more load-shedding.